
Myanmar - 66kV Power Transmission Tower 2022.07
Project Name:Myanmar - 66kV Power Transmission Tower 2022.07
The Customer found us via Alibaba In September 2021 for inquiry 66kV angle steel lattice power transmission tower.
We carry out setting out, blanking, production, inspection, assembly, shipment according to the customer's drawings, and finally reach the customer's hands. We maintain close communication with the customer throughout the whole process to ensure that the customer can understand any progress of the tower.
Address:Myanmar Date:07-07-2022

Mongolia - 20meters 4 legged telecommunication tower 2022.03
Project Name:Mongila - 20meters 4 legged telecommunication tower
The Customer found us via Alibaba In December 2021 for inquiry 4 legged self supporting 20meters telecom tower.
A total of 20 iron towers with a height of 20 meters are designed, produced and processed according to the customer's drawings, and packaged and shipped according to the customer's requirements
Address:Mongolia Date:03-15-2022

Nicaragua - 33kV Transmission line tower 2021.11
Project Name:Nicaragua 33KV Power Transmission Tower 30M Height Project
After two months of unremitting efforts by the salesman, we finally reached a cooperation with Nicaragua to supply 25m high 33kV power tower and promote the power infrastructure construction of Nicaragua。
Address:Nicaragua Date:04-18-2021

Myanmar - 11kV Transmission Line Tower 2021.10
Project Name:Myanmar - 11kv Transmission Line Tower 2021.10
Myanmar Mr Yao find XYTOWER from Alibaba,After the unremitting efforts by the sales Darcy, we finally reached a cooperation with Myanmar to supply low voltage 11kV power transmission line tower and promote the power infrastructure construction of Myanma.
Address:Myanma Date:10-2021

Myanmar - 11kV Electric Power Transmission Tower 2021.06
Project Name:Myanmar 11KV Power Transmission Tower 27M Height Project
Myanmar Padauk Co.,Ltd found us via Alibaba.com on August,2020 for purchasing 8 sets towers for crossing river.
After about 10 days communication,they decide adopt our drawing we recommend according to their specifications & requirement ,then sent the PO to us.
Address:Myanmar Date:02-06-2021

Mongolia - 60meter Telecom Tower 2021.06
Mr Aibolat found us via Alibaba on April 2021 for inquiry 4 leg 60meter telecom tower.
Due to the epidemic, their project has been behind schedule for several months. Therefore, this purchase was very urgent, requiring us to produce within one month and deliver it to Eren hot, the border between Mongolia and China.
A few days after the first communication, he placed the order with us, and we completed the production and
deliver it on time.
Photo sent by the customer after the project completed
Address:Mongolia Date:23-06-2021

Philipines - 30meter Tower for Golf Driving Range 2020.03
On March 2020.Mr H contacted XY towers via ALIBABA for golf driving range towers.Each tower carries a net wall weighing 100 kg acting vertically and a ceiling net weighing 30 kg at top of each tower at right angles across to next tower.After many times negotiation with Mr H about details on vertical and horizontal load capacity and pricing details .
Accroding to Mr H's information.XY designed a three-legged tower for Mr. H. Each tower weighs about 5 tons,totally around 200tons .Pcitues offered by Mr H after one site were completed.
Address:Mongolia Date:18-03-2020

Laos - 10KV Iron Accessories 2021.01
Project Name:Laos - 10KV Iron Accessories 2021.01
Our Company Provides Laos Customer with Power Transmission Tower Iron Accessories,Total Weight : 540 tons.The Order is Signed in January 2021, and the Production Time is 22 Days. It has been Put into Operation Normally in Early April 2021.
Address:Laos Date:01-10-2021

Iraq- 132kV Electric Power Tower 2020.10
Project Name:Iraq 132kV Power Transmission Tower
According to the design drawings provided by customers, we analyzed them, and then started production and processing. After processing, we carried out assembly test, and tested whether the materials meet the standards, which was unanimously satisfactory to customers.
Address:Iraq Date:06-10-2020

Sri Lanka - Electric Substation Structure 2020.08
Project Name:Sri Lanka - Electric Substation Structure Project
We Have Cooperation with Sri Lanka Customers in This Project, with a Total Weight of 130 Tons, The Order is Signed in March 2021, and the Production Time is 40 Days. It has been Put into Operation Normally in Early April 2021.
Address:Sri Lanka Date:23-08-2020

Surinam - Iron Accessories 2020.03
Project Name:Surinam - Iron Accessories Stay Rods 2020.03
We Have Cooperation with Surinam Customers in iron accessories supplying, with a Total Weight of 50 Tons, The Order is Signed in February 2020, and the Production Time is 30 Days. It has been Put into Operation Normally in Early February 2020.
Address:Surinam Date:08-03-2020
Mongolia –110kV Galvanized Steel Tower 2019.12
General area: Mongolia, the new construction of 110k double loops on the user side of Mongolia project. Wire:JL/G1A-240/30.Ground wire: OPGW-24B1-80. The total length of the line is 11KM, Total quantity:angle steel tower is 35 sets. Total weight : 483 tons. The order is signed in September 2019, and the production time is 22 days. It has been put into operation normally in early March 2020.
Address:Mongolia Date:03-14-2020