• bg1

Some Recent Projects

baba0069032356bfc3546b78908e358_副本

Philipines - 30meter Tower for Golf Driving Range 2020

On March 2020.Mr H contacted XY towers via ALIBABA for golf driving range towers.Each tower carries a net wall weighing 100 kg acting vertically and a ceiling net weighing 30 kg at top of each tower at right angles across to next tower.After many times  negotiation with Mr H about details on vertical and horizontal load capacity and pricing details .

Accroding to Mr H's information.XY designed a three-legged tower for Mr. H. Each tower weighs about 5 tons,totally around 200tons  .Pcitues offered by Mr H after one site were completed.

 

Address:Mongolia  Date:18-03-2020
蒙古3

Mongolia - 15meter Telecom Tower 2021.6

Mr Aibolat found us via Alibaba on April 2021 for inquiry 4leg 15meter telecom tower.

Due to the epidemic, their project has been behind schedule for several months. Therefore, this purchase was very urgent, requiring us to produce within one month and deliver it to Eren hot, the border between Mongolia and China. 

A few days after the first communication, he placed the  order with us, and we completed the production and 
deliver it on time. 
Photo sent by the customer after the project completed

Address:Mongolia  Date:23-06-2021
1bc_副本

Myanmar - 11kv Transmission Line Tower 2021.06

Project Name:Myanmar 11KV Power Transmission Tower 27M Height Project

Myanmar Padauk Co.,Ltd found us via Alibaba.com on August,2020 for purchasing 8 sets towers for crossing river.

After about 10 days communication,they decide adopt our drawing we recommend according to their specifications & requirement ,then sent the PO to us.

Address:Myanmar  Date:02-06-2021

微信图片_202108251152152_副本

Nicaragua - 33KV Transmission line tower 2021.04

Project Name:Nicaragua 33KV Power Transmission Tower 30M Height Project

After two months of unremitting efforts by the salesman, we finally reached a cooperation with Nicaragua to supply 25m high 33kV power tower and promote the power infrastructure construction of Nicaragua。

Address:Nicaragua  Date:04-18-2021

01

Yazhong Jiangxi ± 800 kV HVDC Transmission Project 2021.02

Project Name:Yazhong Jiangxi ± 800 kV HVDC Transmission Project 

We Have Cooperation with Sichuan Electric Power Transmission and Transformation Construction Co., Ltd. in This Project, with a Total Weight of 70 Tons, The Order is Signed in February 2021, and the Production Time is 22 Days. It has been Put into Operation Normally in Early April 2021. 

Address: Yazhong,Sichuan   Date: 02-19-2021

94f315d38af7c0ffbc403dc83a8ef2d_副本

MianYang - 10KV Iron Accessories 2021.01

Project name:10KV Iron Accessories Project of State Grid Mianyang Power Supply Company

The Project Cooperate with The State Grid Mianyang Power Supply Company, Providing them with Power Transmission Tower Iron Accessories,Total Weight : 540 tons.The Order is Signed in January 2021, and the Production Time is 22 Days. It has been Put into Operation Normally in Early April 2021.

Address:Mianyang Sichuan   Date:01-10-2021

 

YunNan-41

YunNan-110kV Transmission Tower 2020.10

Project name:110 kV power transmission and transformation project of Shabao Agricultural Photovoltaic Power Station in Nayong County

Adress:BiJie city,YunNan  Date: 25-10-2020

c6a0fef9083ac2e25de3df8ba964053

Hill area -110kV Transmission Tower 2020.09

The new construction of the 110kV line from Quxian Xicheng to Langya, Wire :JL/G1A-300/40-24/7 steel core aluminum stranded wire, ground wire:JLB20A-80, OPGW-24B1-80. Total length of the line is 29KM, the angle steel tower is 90 bases, Toatl weight is 550 tons. The order was  signed in September 2020 until delivery in October 2020, and the cycle was 35 days. It has been put into operation normally in early December 2020.

Address:from Quxian Xicheng to Langya   Date:09-03-2020

3

Hill area – 220kV Power Transmission Tower   2020.6

Huarun Yuexi Sigan Baozu 84MW Wind Power Project 220kV single line project, Wire :JL/G1A-300/40-24/7, Ground wire :OPGW-24B1-80. Total length of the line is 19.35KM, Total quantity of angle steel tower is 45 sets, Total weight is 680 tons. The order is signed in May 2020 to delivery in June 2020, and the production time is 25 days. It will be put into operation normally in early November 2020.

Hill area  (4)

Hill area -35kV Transmission Steel Tower 2020.5

For the new construction project from 110kV Wumu Station to Longyanjing 35kV in Suining, Sichuan, the wire adopts JL/G1A-300/25 and the ground wire adopts OPGW-24B1-50. Total length of the line is 9.5KM, the angle steel tower and the steel pipe pole are 30 bases, Total weight is 260 tons. The order was signed in April 2020 to delivery in May 2020, and the cycle was 25 days. It has been put into operation normally in August 2020.

Address:from Wumu Station to Longyanjing Suining, Sichuan   Date:08-17-2020

20200424094534

High-altitude Area 110kV Lattice Tower 2020.1

Newly-built single-circuit line project in Wangda~Bitu 110kV, Zuogong city,Tibet,conductor JL/G1A-185/35-26/7 ground line GJ-70, the total length of the line is 126KM.Total quantity angle steel tower is 311 sets, Total weight is 3150 tons . It took 90 days after the order was signed in October 2019 to the completion of the delivery of the tower in January 2020, and the entire line was put into operation in August 2020.

Address:Zuogong Tibet   Date:08-03-2020

r7

General area –220kV Galvanized Steel Tower 2019.12

General area: Mongolia, the new construction of 110k double loops on the user side of Mongolia project. Wire:JL/G1A-240/30.Ground wire: OPGW-24B1-80. The total length of the line is 11KM, Total quantity:angle steel tower is 35 sets. Total weight : 483 tons. The order is signed  in September 2019, and the production time is 22 days. It has been put into operation normally in early March 2020.

Address:Mongolia  Date:03-14-2020