General area –220kV  2019.12

General area: Mongolia, the new construction of 110k double loops on the user side of Erlianhot microgrid project. Wire:JL/G1A-240/30.Ground wire: OPGW-24B1-80. The total length of the line is 11KM, Total quantity:angle steel tower is 35 sets. Total weight : 483 tons. The order is signed  in September 2019, and the production time is 22 days. It has been put into operation normally in early March 2020.

p5
p6
p1

Project name:Mongolia 110kV substation project
Tower No.:N43 hoisting
Date:2019.12.14

p2

Project name:Mongolia 110kV substation project
Tower No.:N43 hoisting
Date:2019.12.14

p3

Project name:Mongolia 110kV substation project
Tower No.:N27 hoisting
Date:2019.12.13